You are handling a time-bound project. During the project review meeting, you find that the project is likely to get delayed due to lack of cooperation of the team members. You would...
Warn the team members for their non-cooperation.
Look into reasons for non-cooperation.
Ask for the replacement of team members.
Ask for extension of time citing reasons.